Federal judge halts Big Bend border construction and stays DHS waivers

A preliminary injunction bars border barriers and related ground disturbance across the Big Bend Sector unless the government follows applicable law, while staying three DHS environmental and cultural-law waivers.

Published
Updated
Event: October 2, 2026

The order reaches the entire Big Bend Sector

U.S. District Judge Kathleen Cardone issued a preliminary injunction on October 2 barring the federal government from constructing border barriers or related infrastructure, or undertaking associated ground disturbance, anywhere in the Big Bend Sector unless it complies with all applicable laws. The two-page order also stays the effect of three Department of Homeland Security waivers covering Big Bend National Park, the Lower Canyons and other parts of the sector for the injunction's duration. [1][4][3]

The order followed an evidentiary hearing and says the plaintiffs showed a likelihood of success on at least one claim, a substantial threat of irreparable injury, and equities and public interest favoring interim relief. It does not identify the successful claim or finally decide the lawsuit; Cardone said a detailed memorandum would follow. Construction complying with applicable law is not prohibited by the text, but the three broad waivers cannot be used while the injunction remains in effect. [1][6][5]

The waived laws covered environmental, cultural and burial protections

DHS invoked Section 102 of the Illegal Immigration Reform and Immigrant Responsibility Act to waive statutes for border construction, saying the projects were needed for operational control. The official notice lists the National Environmental Policy Act, Endangered Species Act, Clean Water Act, National Historic Preservation Act, Migratory Bird Treaty Act and Native American Graves Protection and Repatriation Act among the federal requirements set aside, along with related regulations and state laws. [2][1]

Plaintiffs include landowners, a preservation group tied to historic Ruidosa Church and a river guide. Local reporting describes concerns about private property, springs, wildlife habitat, archaeological sites and culturally significant land. Reuters and AP reported that planned infrastructure included not only wall segments but also roads, vehicle barriers and surveillance technology. The precise mix varies by location, so the ruling should not be read as saying a 30-foot wall was planned for every mile of the sector. [5][6][3][4]

The government can appeal, and a separate lawsuit had a different result

Customs and Border Protection told AP and local public radio that the government was reviewing the order with the Justice Department and remained confident in its legal authority. The agency has defended construction as a border-security measure. The injunction does not erase that policy position; it requires the government to proceed under laws that the stayed waivers had displaced unless a higher court or later district-court ruling changes the result. [4][6][2]

The Big Bend Sentinel reported that another federal judge denied a temporary restraining order in a separate challenge brought by environmental organizations, an important procedural difference rather than a contradiction about the same plaintiffs. Spanish-language reporting by El Pais described the injunction and regional scale; names, dates, distance conversions and the preliminary posture were checked against the English order and U.S. reporting. The next decisive documents will be Cardone's full reasoning and any government appeal. [5][7][1]

How the sources compare

SourceWhat it addsScope or limitation
U.S. District Court for the Western District of Texas · EnglishThe operative scope, stayed waivers and preliminary-injunction findings in the signed October 2 order.The two-page order defers detailed legal reasoning to a forthcoming memorandum and does not decide final liability.
Reuters and Associated Press · EnglishIndependent national reporting on the order, project components, parties' positions and government response.Both reports describe preliminary relief; neither supplies the court's still-unreleased detailed merits analysis.
Big Bend Sentinel and Marfa Public Radio · EnglishLocal courtroom reporting, affected land and community context, the separate lawsuit, and the practical reach of the sector-wide order.The Texas Tribune version of the Sentinel report is a republication and is counted as the same reporting origin, not independent corroboration.
Department of Homeland Security, Federal Register notice · EnglishThe government's asserted statutory authority and the exact environmental, historic-preservation and cultural-protection laws it waived.The notice states the executive branch's justification; it does not resolve the plaintiffs' legal claims or the injunction's validity.
El Pais · Spanish, translated and checked against English recordsOriginal Spanish-language reporting on the affected region, litigation and cross-border significance.It summarizes the U.S. proceeding and adds no independent judicial reasoning beyond the English-language order.

What remains unclear

Which claim or claims Judge Cardone concluded were likely to succeed; the detailed memorandum was not yet public.

Whether the government will appeal or seek to narrow or stay the injunction.

The final configuration, cost and schedule of projects if the government proceeds under applicable laws.

How related eminent-domain disputes and the separate environmental lawsuit will affect particular parcels.

Sources & translations

  1. U.S. District Court for the Western District of Texas, copy hosted by Center for Biological Diversity — Friends of Ruidosa Church v. Mullin, order granting preliminary injunctionOctober 2, 2026 · English · Primary court record
  2. U.S. Department of Homeland Security, Federal Register — Determination Pursuant to Section 102 of the Illegal Immigration Reform and Immigrant Responsibility Act of 1996June 18, 2026 · English · Primary government notice
  3. Reuters — Judge bars building Texas-Mexico border barrier in Big Bend National ParkOctober 3, 2026 · English · International legal reporting
  4. Associated Press — Federal judge temporarily blocks border wall construction in Texas' Big Bend regionOctober 2, 2026 · English · Independent U.S. reporting
  5. The Big Bend Sentinel — El Paso judge issues injunction in Big Bend border wall suitOctober 2, 2026 · English · Independent local courtroom reporting
  6. Marfa Public Radio — Judge halts Big Bend-area border wall construction, use of federal waiversOctober 2, 2026 · English · Independent local public-radio reporting
  7. El Pais — Una jueza federal paraliza la construccion del muro fronterizo de Trump en el Parque Nacional Big Bend y alrededoresOctober 3, 2026 · Spanish · Original Spanish-language international reportingReviewed in Spanish; legal posture, names, dates and geographic figures were checked against the English court order and U.S. reporting.

Updates & corrections

  • — Initial report adds the signed order, federal waiver notice, local courtroom reporting and Spanish-language coverage to a topic previously held for insufficient documentation.